Willow Park pavillion

 /  Our Major ProjectsWillow Park pavillion

Willow Park pavillion


Additional space for sports training and community activities during the winter months are just some of the benefits that the new pavillion at Willow Park will boast.

The facility, which will be demolished early October, 2019 will replace the existing pavillion to provide upgraded amenities and to accommodate greater female participation.

The upgrade to the pavillion was funded in conjunction with the flood lighting upgrade late last year. 

The project is estimated for completion in 2020 and is being completed by Wodonga Council in partnership with the Victorian Government through the Community Sports Infrastructure Fund (Female Friendly Facilities).

Timeline
  • Works update
    November 25, 2019

    Plumbing and electrical is under way with roofing well advanced.

    It is on track for completion by the end of December 2019.

  • Works update
    October 1, 2019

    Underground services, such as plumbing, electrical and drainage has started to be installed.

    The concrete slab will be prepared in the coming days

  • Works update
    September 24, 2019

    The surface has been prepared for construction to commence

  • Demolition started
    September 16, 2019

    Works to the Willow Park pavillion officially commenced today with the demolition of the existing site