Kelly Park netball courts


The regional netball facility at Kelly Park is used by Netball Wodonga for junior competitions and training as well as regional netball clubs that use the venue for training.

The deterioration of the surface of the courts as well as other compliance issues that exist at the venue has made it necessary to undertake upgrades. Works included in the whole project include the replacement of the court surface, upgrades to floodlighting and the provision of shelters and seating to support spectators and participants. An allocation was made in the 2017/18 council budget to address these issues.

Netball Wodonga are contributing $120,000 towards the project. Council engaged a specialist sporting design consultant - SportEng to prepare design plans and specifications for this project as a requirement from the funding partner.

The tender advertised in the Border Mail and via TenderSearch on Saturday, September 16, 2017, covered the remediation and replacement of the court surface within the existing footprint and will result in nine compliant courts at Kelly Park. Further tenders are to be issued to complete the upgrade of the floodlighting and provision of shelters and seating at the venue.

After all assessments, the panel considered that the tender submission from Excell Gray Bruni Pty Ltd provided the best value for money option for the council.

Excell Gray Bruni Pty Ltd have completed a number of civil construction projects recently for council to an acceptable standard, within expected timeframes and allocated budgets.

They have been assessed as having the capability to deliver this project within the required timeframes and quality of the finished project

Timeline
  • Works complete
    March 23, 2018
    After the base works were complete, the asphalt surface was the finishing layer for the new courts.

    This means that the reinstatement works could commence, which included laying instant turf, a concrete footpath, installation of the goal posts and linemarking.

    The project was handed over to Wodonga Netball on March 23, 2018.

  • Drainage pits installed
    February 22, 2018
    Installation of drainage pits, spoon drains, grated drains and sub-soil drainage works completed.
  • Sub-base works complete
    January 22, 2018
    Since the commencement of construction, the old asphalt surface has been completely ripped off, we have removed asbestos drainage pipes from the site and completed subgrade replacement works.
  • Demolition commenced
    December 5, 2017
    Demolition of old asphalt surface has commenced.

    The site is fenced out to restrict public access as we removed the old netball posts, shelters and trees.